The French Australian Preschool project involved construction services to Stage 1 and Stage 2 of the compliance and condition upgrades, which were designed to meet long-term objectives of the Preschool.

Stage 1 consisted of an “Administration Wing” expansion to the existing building which has created spaces for the director’s office, administration personnel, amenities and reception area. Stage 1 also included the construction of a 310m2 standalone building which hosts 2 additional classrooms, amenities, and large bag storage area.

Stage 2 involved the demolition of the existing linkway, entrance and cladding faҫade. Hardstands and double skin blockwork with a new cladding faҫade was then installed to upgrade the appearance of this area.

The quality finishes selections for the French Australian Preschool required Projex to take special consideration when procuring our subcontractors to install these products.  Each element of the build was highly detail and was delivered inside the project program.

  • Client Tuner Townsend
  • Architect/Referee Clarke Keller
  • Project Value $2.3M
  • Delivery Model Project Management
  • Project Sector Education
  • Duration 24 Weeks
Projex achieved a high level finish throughout the project, due to close liaison with the architect, and injecting significant amounts of resources into ensuring the finish was consistently at a high distinction.